New crossing from M25 J29/A13 (Essex) to the A2/M2 (Kent), twin bored tunnels · South East / East
Delivery: Balfour Beatty (Roads North); Bouygues TP-Murphy JV (Tunnels and Approaches); Skanska (Kent Roads)
Under construction; work began early 2026 (NH news 30 Sep 2026); RIS3 includes £1.65bn publicly-funded works
A66 from the M6 at Penrith to the A1(M) at Scotch Corner (dualling 18 miles) · North West / Yorkshire and North East
Delivery: Delivery Integration Partners: Kier Highways, Keltbray Highways, Balfour Beatty, Costain
DCO approved 7 Mar 2024; archaeology and utilities preparatory works; named in RIS3
A428 / A1 (10-mile new dual carriageway) · East (Bedfordshire/Cambridgeshire)
Delivery: Skanska (design and build), Mott MacDonald design partner; £507m contract via the Regional Delivery Partnership
Under construction; on track to open spring 2027 (Skanska 2025 release)
M67 to A57 Mottram Moor (Mottram underpass) · North West (Tameside, Greater Manchester)
Delivery: Balfour Beatty (£108m design and build via the DIP framework, 2020), Atkins design partner
Under construction (piling for the Mottram Underpass; plant crossings from May/June 2026)
A417 Brockworth bypass to Cowley roundabout · South West (Gloucestershire)
Delivery: Kier (main contractor, £460m); designed by Arup and the Professional Services Alliance (Kier Design, Tony Gee, RPS)
Under construction (DCO granted 16 Nov 2022; temporary route summer 2026)
M3 J9 / A34 / A33, Winchester · South East (Hampshire)
Delivery: Not named on the NH page (Balfour Beatty's 2025 annual report mentions a JV for this scheme; not verified)
Under construction; early works from 11 Oct 2024; cost £268m-£322m; end date Road Period 3
M25 J28 / A12 Brook Street · Essex (listed under NH South East projects)
Delivery: GRAHAM (named as delivery partner on the NH page)
Main on-road construction complete Oct 2025; finishing works (Mar 2026 update); cost £140m-£170m
A47 dualling · East (Norfolk)
Delivery: Galliford Try (£300m; works began Oct 2024)
Under construction; end date 2026-27; cost £100m-£250m (NH)
A47 dualling · East (Norfolk)
Delivery: Galliford Try
New dual carriageway fully open 6 May 2026; finishing works Oct 2026; cost £90m-£100m
M60 / M62 / M66 · North West (Greater Manchester)
Delivery: Not named on the NH page
DCO approved 9 Sep 2025
A46 Farndon to Winthorpe · Midlands (Nottinghamshire)
Delivery: Not named on the NH page
DCO approved 1 Oct 2025
A38 Kingsway, Markeaton and Little Eaton junctions · Midlands (Derby)
Delivery: None; the NH page says it will start the process of appointing a new contractor
DCO re-granted 17 Aug 2023; legal challenge concluded in NH's favour; construction start not announced
M54 J1 to M6 J11 / M6 Toll · Midlands (Staffordshire)
Delivery: None; BAM Nuttall's involvement ended and NH is appointing a new delivery partner
DCO granted 21 Apr 2022; awaiting a new delivery partner
A12 J19-J25 · East (Essex)
CANCELLED by the Government after the Spending Review (NH update 1 Aug 2025); DCO had been granted 12 Jan 2024